The Venture Smart team specialise in managing the logistical challenges of removal, installation and replacement of critical electrical infrastructure on the Main Roads Western Australia (MRWA) network.
A recent project saw the team delivering a large project that included street lighting, Principal Shared Path (PSP) lighting and live edge protection permanent fencing in and around the state government's Parliament House on the Mitchell Freeway.
Project scope
The project included:
- Installation of two new switchboards, new lighting and associated cabling on the outside verges of the Mitchell Freeway between Mount Street and Murray Street
- Removal of existing lighting poles and asbestos pits on the median strip
- Replacement of under bridge lighting at the Malcolm Street, Hay Street and Murray Street bridges
- Installation of new lighting and associated cabling on the east and west side of the Mitchell Freeway, notably along the WA Parliament House boundary
- Replacement of PSP lighting at the Malcolm Street underpass
- Installation of in-ground lighting under Mount Street and removal of existing lighting
- Installation of around 470 metres of in-ground mounted balustrades and 700 metres of wall-mounted handrails.
Managing a complex site
The location of the installation and replacement activity meant that the times available to undertake work were constrained by morning and evening peak hour traffic restrictions, as well as restrictions due to PSP stakeholder requirements.
There were also environmental challenges with the site, such as 'dieback' - where there are issues of vegetation disease, which requires a site management plan to mitigate the spread to other areas.
A final challenge involved the extension of the area included in the project, introducing a need for additional permit requirements and an impact on scheduling. The team's ability to be flexible and manage a change in scope after the project had commenced was demonstrated by an avoidance of delays, and a delivery of the project on time and on budget via a strong change control process.