| Commenced: 2023
Ventia performs operational and maintenance activities including substation maintenance, inverter maintenance, panel and structure inspection, thermal imaging of panels (using drones), panel cleaning and facility management.
In addition, we are performing Supervisory Control and Data Acquisition (SCADA) system monitoring and control, which is utilising our Ventia Operations Centre (VOC) expertise, a key differentiator for our business.
The West Wyalong solar farm has been delivered by PCL Solar Australia, through investment from the asset owner Lightsource bp and incorporates 15 power conversion units, 425 combiner boxes, 33,501 piles (supporting the solar arrays) and 200,284 modules.
The farm will generate 238,000 MWh of clean renewable electricity each year (equivalent to the usage of 42,034 homes annually) and will supply renewable energy to 88 of bp's service stations across NSW.